软题库 培训课程
当前位置:信管网 >> 综合知识 >> 文章内容
高项英语复习:英语试题连载(八)
来源:信管网 2013年10月29日 【所有评论 分享到微信

Project Quality Management processes include all the activities of the ( ) that determine quality policies, objectives and responsibilities so that the project will satisfy the needs for which it was undertaken.
A、project
B、project management team
C、performing organization
D、customer
项目质量管理过程包括保证项目满足原先规定的各项要求所需的实施组织的活动,即决定质量方针、目标与责任的所有活动。

The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned ,designed and built in, not ( ).
A、executed in
B、inspected in
C、check-in
D、look-in
项目团队成员应该注意到现代质量管理的一条基本准则是:质量是计划、设计出来的,不是检查出来的。

The project ( ) is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements, thresholds, and acceptance criteria.
A、work performance information
B、scope statement
C、change requests
D、process analysis
项目范围说明书是制订质量计划的一项关键输入,这是因为它记载了项目的主要可交付成果以及用于确定重要项目干系人需求的项目目标、限值和验收标准。

Performing ( ) involves monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory results.
A、quality planning
B、quality assurance
C、quality performance
D、quality control
执行质量控制指监控具体的项目结果,确定其是否符合相关的质量标准,并判断如何杜绝造成不合格结果的根源。

( ) involves using mathematical techniques to forecast future outcomes based on historical results.
A、Trend analysis
B、Quality audit
C、Defect repair review
D、Flowcharting
趋势分析指根据过去的结果使用数学方法预测未来成果。

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。