The creation of a work breakdown structure(WBS)is the process of ( ) the major project deliverables.
A、subdividing
B、assessing
C、planning
D、integrating
创建工作分解结构是分解项目可交付物的过程。
选项A是分解,选项B是估算,选项C是计划,选项D是整合。
Many of the activities performed during the preliminary investigation are still being conducted in ( ), but in much greater depth than before. During this phase, the analyst must become fully aware of the(-)and must develop enough knowledge about the(-)and the existing systems to enable an effective solution to be proposed and implemented.Besides the(-)for process and data of current system, the deliverable from this phase also includes the(-)for the proposed system.
A、analysis phase
B、design phase
C、implementation phase
D、maintenance phase
在初步调研时完成的许多活动在分析阶段还要继续进行,只是比以前更深入地去做。在这个分析阶段,系统分析师一定要充分注意到问题的根源,并且充分掌握关于业务环境和现行系统的知识,以提交和实施一个有效的解决方案。除了提交现行系统的过程和数据的逻辑模型外,这一分析阶段的交付物还包括推荐系统的正式需求定义。
英语日积月累
( )is primarily concerned with defining and controlling what is and is not included in the project.
A、Project Time Management
B、Project Cost Management
C、Project Scope management
D、Project Communications Management
( )是最先定义和决定项目中包含哪些内容和确定边界的。
A、项目时间管理
B、项目成本管理
C、项目范围管理
D、项目沟通管理
Primarily:首先
Concerned:有关
英语日积月累
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
A、assign change tasks to project members
B、call a meeting of the configuration control board
C、change the scope baseline
D、postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
项目经理认为调整项目范围可以给客户提供增值的服务,项目经理应该( )。
A、安排任务变更到项目成员
B、召集变更控制委员会会议
C、变更项目基线
D、按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改
Modify:改变
added value service:增值服务
assign:安排
postpone:延缓
separate:分开的
enhancement:增加
funded:(为某一特定目的给予的)资金
according:依照