The project life-cycle can be described as ( ).
A、project concept, project planning, project execution, and project close-out
B、project planning, work authorization, and project reporting
C、project planning, project control, project definition, WBS development, and project termination
D、project concept, project execution, and project reporting
项目生命周期划分正确的是( )。
A、启动、计划、执行、收尾
B、计划、授权、报告
C、计划、控制、方案设计、WBS的发展、终止
D、启动、执行、报告

A project life cycle is a collection of generally sequential project ( ) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic (-) for managing the project, regardless of the specific work involved.
A、phases
B、processes
C、segments
D、pieces
一个项目的生命周期由若干个顺序相连的( )组成,阶段的名字和个数由组织的控制需要决定,项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的(-)。
A、阶段
B、过程
C、片段
D、碎片

A project life cycle is a collection of generally sequential project (-) whose name and number are determined by the control needs of the organization or organizations involved in the project. The life cycle provides the basic ( ) for managing the project, regardless of the specific work involved.
A、plan
B、fraction
C、main
D、framework
一个项目的生命周期由若干个顺序相连的(-)组成,阶段的名字和个数由组织的控制需要决定,项目涉及到的其他组织,其控制需要也可决定项目阶段的名字和个数。无论涉及到的具体的工作有哪些,项目的生命周期都为管理项目提供了基本的( )。
A、计划
B、部分
C、主体
D、框架

Estimating schedule activity costs involves developing an (-) of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives.for example,in mostapplication areas,additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product oprations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estmates are generally expressed in units of (-) to facilitate comparisons both within and across projects. the ( ) describes important information about prject requirement that is considered duing cost estimating.
A、project scope statement
B、statement of work
C、project management plan
D、project policy
估算计划活动的成本涉及估算完成每项计划活动所需资源的近似成本。成本估算包括识别和考虑各种成本计算方案。例如,在大多数的应用领域,普遍在设计阶段多做些额外工作以降低执行阶段和产品运行时的潜在成本。成本估算过程考虑预期的成本节省是否能够弥补额外设计工作的成本。成本估算一般以货币单位表示,以利于在项目内和项目间进行比较。项目范围说明书描述了项目的商业要求、理由、需求和当前边界。它提供了关于在成本估算时必须考虑的项目需求的重要信息。

The ( ) technique involves using project characteristics in a mathematical model to predict total project cost.models can be simple or complex.
A、cost aggregation
B、reserve analysis
C、parametric estimating
D、funding limit reconciliarion
参数估算涉及在一个数学模型中利用项目特性来预测整体项目成本。模型可以是简单的也可以是复杂的。

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章