Precedence Diagramming Method(PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM. The initiation of the successor activity depends upon the completion of the predecessor activity is called (  ).
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish


相关试题

66题:

某软件企业2006年初计划投资2000万人民币开发某产品,预计从2007年开始盈利,各年产品销售额如表所示。根据表中的数据,该产品的静态投资回收期是(1)年,动态投资回收期是(2)年。(提示:设贴现率为0.1)

(1)A.1.8                            B.1.9                        C.2                         D.2.2
(2) A.2                              B.2.1                        C.2.4                      D.3

答案解析与讨论:www.cnitpm.com/st/758261.html

67题:

Documentation of a software package is normally produced for two purposes.One is to explain the (1) of the software and describe how to use them.This is known as (2  )because it is designed to be read by the user of the software.The other purpose of documentation is to describe the software’s internal composition so that the system can be maintained later in its lifecycle.Documentation of this type is knownas (3).
(1) A.plans
B.cost
C.features
D.schedules
(2)A.system documentation
B.user documentation
C.vender documentation
D.product documentation
(3)A.system documentation
B.user documentation
C.vender documentation
D.license documentation

答案解析与讨论:www.cnitpm.com/st/759262.html

68题:

Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria. (  )is not a project selection method.
A.Benefit contribution
B.Expert judgment
C.Scoring models
D.Flow charting

答案解析与讨论:www.cnitpm.com/st/760262.html