Which of following is an important input to scope verification? ( )
A、Work results
B、Historical information
C、Formal acceptance
D、Change request


相关试题

71题:

( ) is the use of computing resources (hardware and software) that a delivered as a service over a network (typically the Internet).
A、Virtualization
B、Internet of things
C、Cloud computer
D、Cloud computing

答案解析与讨论:www.cnitpm.com/st/43661503.html

72题:

The work that needs to be accomplished to deliver a product, service ,or result with the specified features and functions is called ( ).
A、Scope management
B、Integrated management
C、SOW
D、PMO

答案解析与讨论:www.cnitpm.com/st/43671504.html

73题:

All of followings should be done by the project manager during project control except ( ).
A、Determine that a change has occurred
B、Ensure that a change is agreed
C、Make sure all changes are approved by management
D、Manage changes as they occur

答案解析与讨论:www.cnitpm.com/st/43681504.html

75题:

Modern computers based on ( ) are millions to billions of times more capable than the early computers, which occupy a fraction of the space. Simple computers are small enough to fit into mobile devices, an mobile computers can be powered by small batteries. Personal computers in their various forms are icons of the Information Age and are what most people think of as ‘computers’.
A、Central Processing Unit
B、integrated circuits
C、Hard disk
D、software integration