A Construction site is damaged by a storm. As a result,the project manager authorize the procurement of replacement materials and additional resource to keep the project on schedule . which document did the project manager use to make this decision?
A、Risk management plan
B、Inventory management plan
C、Procurement plan
D、Quality management plan