The project is close to completion. All project deliverable have been accepted by the stakeholders. The program manager has asked the project manager to take on another project. All external contracts have been met and all the contracts closed.What should the project manager do?
A、Announce the project is closed and move to the new project.
B、Ensure that all procedures to transfer the project’s products and service to production are in place.
C、Conduct an external review of the project by a team of experts.