A company will be replacing its integrated systems after 10 years of service from a legacy platform that on longer meets market needs. During project planning, managers identify a more flexible pricing structure as a key requirement. Senior managers have not yet decided how to meet this requirement but agree it is strategically correct. During project execution, changes in the pricing structure will require frequent rework and retesting. Which of the following is an element of the project plan that addresses this in a systemic way?
A、A quality policy requiring project changes to be approved by senior managers
B、A risk response plan that would identify risks from new requirements
C、A staff augmentation plan to implement pricing structure changes
D、A scope statement with detailed requirements for implementation