The project team prepares a chart linking the categories and subcategories of identified risks. The team is creating which of the following?A、Risk registerB、Risk breakdown structureC、Qualitative risk analysisD、Quantitative risk analysis
信管网参考答案:B(仅供参考,欢迎评论交流) 收藏