During an informal conversation with a project team member,the project manager discovers that a supplier for a key part has problems implementing an approved product change. Which of the following should the project manager do next ?
A、Perform a quality audit of the supplier.
B、Schedule a change control meeting.
C、Measure the supplier’s work performance.
D、Speak with a senior manager of the supplier.