During project planning, the project team identifies a new technical risk. Since the project team uncertain they can identify an appropriate solution to meet a deadline the schedule is extended with the customer’s approval. What type of risk resource strategy does the project manager use ?
A、Share
B、 Avoid
C、 Accept
D、 Transfer