You have always been asked by your management to cut your project estimate by ten percent after you have given it to them. The scope of your new project is unclear and there are over 30 stakeholders. Management expects a 25 percent reduction in downtime as a result of the project. Which of the following is the BEST course of action in this situation?
A、Re-plan to achieve a 35 percent improvement in downtime.
B、Reduce the estimates and note the changes in the risk response plan.
C、Provide an accurate estimate of the actual costs and be able to support it.
D、Meet with the team to identify where you can find lo percent savings.

试题出处:http://www.ruantiku.com/shiti/352375376.html
在下面提交答题后即可查看答案与考友试题分析
我的答案与分析  查看全部答题与分析  

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

推荐文章