The project manager can arrange the project schedule management activities in the following order()。
①Plan schedule Management    ②Define Activities
③Estimate Activity Durations     ④Sequence Activities
⑤Control Schedule    ⑥Develop Schedule
A.①②③④⑤⑥
B.②④③⑥⑤①
C.①③④②⑥⑤
D.①②④③⑥⑤

查看答案

相关试题

71题: New information technology includes  ()
A.Date   Engineering
B.Information  Security
C.Metaverse
D.Artificial  Intelligence
答案解析与讨论:www.cnitpm.com/st/5688915290.html

72题: ()are the major issue that mobile Internet needs to face and deal with.
A.storage and computing
B.Communications and transmission
C.Date security and privacy protection
D.intelligent application and interface interaction
答案解析与讨论:www.cnitpm.com/st/5689027102.html

73题: ()is the input of project quality management.
A.project management plan
B.Data Analysis
C.Risk register
D.Test report
答案解析与讨论:www.cnitpm.com/st/5689121776.html

75题: The information security attribute and objectives are()。
A.Confidentiality , Integrity, and Availability
B.Confidentiality , Non-repudiation and shareability
C.Confidentiality , Stability and Availability
D.Confidentiality , Non-repudiation and Availability
答案解析与讨论:www.cnitpm.com/st/5689312619.html