第
72题: ()are the major issue that mobile Internet needs to face and deal with.
A.storage and computing
B.Communications and transmission
C.Date security and privacy protection
D.intelligent application and interface interaction
答案解析与讨论:
www.cnitpm.com/st/5689027102.html第
73题: ()is the input of project quality management.
A.project management plan
B.Data Analysis
C.Risk register
D.Test report
答案解析与讨论:
www.cnitpm.com/st/5689121776.html第
74题: The project manager can arrange the project schedule management activities in the following order()。
①Plan schedule Management ②Define Activities
③Estimate Activity Durations ④Sequence Activities
⑤Control Schedule ⑥Develop Schedule
A.①②③④⑤⑥
B.②④③⑥⑤①
C.①③④②⑥⑤
D.①②④③⑥⑤
答案解析与讨论:
www.cnitpm.com/st/5689224625.html