信管网公众号
信管网订阅号
Estimating activity durations uses information on activity scope of ( ), required resource types, estimated resource quantities, and resource calendars.A. milestone B. baseline C. quality D. work
信管网参考答案:D(仅供参考,欢迎评论交流) 收藏
考试信息推送
免费在线答题
优惠报班活动
直播录播辅导