In project management and systems engineering, (     ) is a deliverable-oriented breakdown of a project into smaller components. It is a key project deliverable that organizes the team's work into manageable sections.
A. RBS 
B. PBS 
C. GBS 
D. WBS


相关试题

71题: () is a programming model and an associated implementation for processing and generating big data sets with a parallel, distributed algorithm on a cluster. The model is a specialization of the split-apply-combine strategy for data analysis.
A. HDFS 
B. Chukwa 
C. MapReduce 
D. HBase
答案解析与讨论://www.cnitpm.com/st/3891923950.html

72题: The IoT architecture can be divided into three layers.  (     ) is the key layer to realize the foundational capabilities which support the electronic devices interact with physical world.
A. Sensing layer 
B. Network layer 
C. Application layer 
D. Operation layer
答案解析与讨论://www.cnitpm.com/st/389204944.html

73题: Project Integration Management includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. (   ) process does not belong to Project Integration Management.
A. Developing project charter 
B. Developing project management plan 
C. Analyzing project risks 
D.Monitoring and controlling project
答案解析与讨论://www.cnitpm.com/st/389212434.html

75题: (     ) is the sum of all budgets established for the work to be performed.
A. CPI 
B. BAC 
C. SPI 
D. EAC
答案解析与讨论://www.cnitpm.com/st/3892314855.html