软题库 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷年份2017年下半年
试题题型【单选题】
试题内容

Diagram 1 shows the sequence of activities for project XYZ and its duration. The project manager is asked to reduce the project duration by two weeks. None of the activities can be fast tracked. Activities A and F cannot be crashed, activity G can be crashed by two weeks; and all other activities can be crashed by one week. To meet the new project duration requirement, which of the following will the project manager decide to do?

A. Crash activity G.
B. Crash activity C and D .
C. Crash activity G, C and D .
D. Crash activity G,F and C .


相关试题