试卷年份2015年下半年
试题题型【单选题】
试题内容

(  )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.
A、Parametric
B、Analogous
C、Three-point
D、Expert judgment


相关试题

66题:

有一种游戏为掷两颗骰子,其规则为;当点数和为2时,游戏者输9元;点数和为7或者11时,游戏者赢X元;其他点数时均输1元。依据EMV准侧,当X超过(  )元时游戏才对游戏者有利
A、3.5
B、4
C、4.5
D、5

答案解析与讨论:www.cnitpm.com/st/2119526065.html

67题:

In an Information system. The(  ) is the bridge between hardware and  people
A、keyboard
B、internet
C、disk
D、data

答案解析与讨论:www.cnitpm.com/st/2119616077.html

68题:

Cloud-computing providers offer their “services” according to different models, which happen to form a stack(  ), platform as a service (Paas), software as a service (SaaS)
A、hardware as a service (Haas)
B、network as a service (NaaS)
C、infrastructure as a service (IaaS)
D、data as a service (DaaS)

答案解析与讨论:www.cnitpm.com/st/211973516.html

70题:

Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and (  )
A、fast tracking    
B、what-if scenario analysis
C、resource leveling   
D、critical chain method

答案解析与讨论:www.cnitpm.com/st/2119918454.html

71题:

If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and(  ) of the project management plan. Are revised and reissued to reflect the approved changes
A、developing baselines
B、testing baselines
C、schedule baselines
D、ending baselines

答案解析与讨论:www.cnitpm.com/st/2120012191.html