软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
试卷年份2011年上半年
试题题型【单选题】
试题内容

The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project ’ s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that (  ).
A.the project is ahead of its planned schedule
B.less work was completed than was planned
C.the cost overrun for work completed
D.the cost under-run of performance to date


相关试题

70题:

TCP/IP communication protocol contains four layers. From bottom to top, the four layers are (  ).
A.network interface layer, internet layer, transport layer and application layer
B.internet layer, network interface layer, transport layer and application layer
C.network interface layer, transport layer, network interface layer and application layer
D.application layer, transport layer, internet layer and network interface layer

答案解析与讨论:www.cnitpm.com/st/1090376.html

71题:

Ethernet is the commonly used local area network communication protocol. The standard of Ethernet is (  ).
A.IEEE 802.1
B.IEEE 802.2
C.IEEE 802.3
D.IEEE 802.11

答案解析与讨论:www.cnitpm.com/st/1091376.html

72题:

(  )are the four major activities of software configuration management.
①configuration identification ②statement report ③change control
④preparation of requirement document ⑤configuration auditing
A.①②③④
B.①②④⑤
C.①②③⑤
D.②③④⑤

答案解析与讨论:www.cnitpm.com/st/1092376.html

74题:

SWOT analysis is a kind of risk identification method. If the project team chose the SO strategy, they should (  ).
A.make full use of the advantage and catch the opportunity
B.overcome the weakness and catch the opportunity
C.make full use of the advantage and reduce the threat
D.overcome the weakness and reduce the threat

答案解析与讨论:www.cnitpm.com/st/1094377.html



推荐文章
合作网站内容