A project manager for a bidding project receives preliminary information from the client in project early stage. The client
requests a fixed-price contract for the entire project. What should the project manager do
A. Estimate the project based on similar project, explain the assumptions, and present a change management plan to the client to
protect the estimate from future scope changes.
B. Estimate the project based on similar protects, and add a reasonable amount of risk contingency to protect the estimate from future
scope changes.
C. Estimate the clearly defined requirements, and present this as a fixed-price compacts to the first part of the project.
D. Estimate the project based on the information available, and initiate claims immediately as soon as any scope changes appear.
我的答案与分析 查看全部答题与分析 | |
|
温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!
信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。
信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。