A project manager for a bidding project receives preliminary information from the client in project early stage. The client
requests a fixed-price contract for the entire project. What should the project manager do
A. Estimate the project based on similar project, explain the assumptions, and present a change management plan to the client to
protect the estimate from future scope changes.
B. Estimate the project based on similar protects, and add a reasonable amount of risk contingency to protect the estimate from future
scope changes.
C. Estimate the clearly defined requirements, and present this as a fixed-price compacts to the first part of the project.
D. Estimate the project based on the information available, and initiate claims immediately as soon as any scope changes appear.

试题出处:http://www.ruantiku.com/shiti/337274484.html
在下面提交答题后即可查看答案与考友试题分析
我的答案与分析  查看全部答题与分析  

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

推荐文章