The following are the project tasks:
Task A (duration 4 days)
Task B (duration 3 days)
Task C (duration 4 days)
Task D (duration 2 days)
Task E (duration 3 days)
Task F (duration 4 days)
Task D and task F can not start until task C is completed.  Task A and task B can start at any time after task C starts, but must complete before the end of the project.  Task E can only starts after task D is completed.  During the execution of task B, which starts 1 day later after task C starts, exception happened which will cause a 2-day delay for task B、 What action should be taken to ensure the project can be completed on time?
A、Add more resources to task B
B、 No action is necessary
C、 Reassign resources to tasks on
D、 Add more resources to task D

试题出处:http://www.ruantiku.com/shiti/3379610500.html
在下面提交答题后即可查看答案与考友试题分析
我的答案与分析  查看全部答题与分析  

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

推荐文章