You are the project manager for a large government contract. The contract was signed a year ago for this tree-year, mufti-million-dollar project. You were not involved in writing the contract or setting up change control procedures, but now you are being inundated with change requests from the project sponsor and from your own senior management. What should you do first ?
A、Tell the sponsor and your senior management that any changes are out of scope at this point and cannot be considered.
B、 Meet with the project sponsor and senior management to discuss this problem and potential solutions.
C、 Talk to your legal department to make sure you doesn’t do anything illegal.
D、 Ask senor management to set aside more management reserve to avoid potential financial problems.

试题出处:http://www.ruantiku.com/shiti/3378829800.html
在下面提交答题后即可查看答案与考友试题分析
我的答案与分析  查看全部答题与分析  

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

推荐文章