A project manager is called to an informal meeting with the customer and a problem is raised. This p
来源:信管网 2014年04月29日 【所有评论 分享到微信

2011年下半年软考中级系统集成项目管理工程师综合知识真题答案与解析:

●A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should(72).
(72)
A.Tell the customer that he will not address any problems
B.Tell the customer that the problem is not sufficiently defined to company to a solution
C.Collect as much information on the problem without committing hiscompany to a solution
D.Give the customer a range of solutions that might be acceptable to his company
信管网解析:
项目经理被调用来与客户的非正式会议和问题提出。这个问题有项目经理所在的公司产生重大影响,但客户要追求solutionat会议上,项目经理应该(72)。
(72)
A.Tell客户,他不会解决任何问题
B.Tell,这个问题是没有充分定义为公司的解决方案的客户
C.Collect上的问题,而不犯hiscompany来解决尽可能多的信息
D.Give客户一个范围,或许可以被接受,他的公司的解决方案
信管网参考答案:C

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章