The ( ) provides the project manager with the authority to apply organizational resources to project activities.
A、project management plan
B、contract
C、project human resource plan
D、project charter
项目章程为项目经理使用组织资源进行项目活动提供了授权。

The ( ) Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A、Planning
B、Executing
C、Monitoring and Controlling
D、Closing
执行过程组由用于完成为达成项目要求而在项目管理计划中定义的工作的过程组成。

( )are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.
A、Project manager
B、Project team member
C、Sponsor
D、Project stakeholders
项目干系人是指那些积极参与项目或是其利益会受到项目执行或完成的结果影响的个人和组织。

The ( ) defines the phases that connect the beginning of a project to its end.
A、schedule
B、project life cycle
C、temporary
D、milestone
项目生命周期定义了从项目开始直至结束的项目阶段。

( ) means that every project has a definite beginning and a definite end.
A、Project phase
B、Unique
C、Temporary
D、Closure
临时性是指每一个项目都有一个明确的开始时间和结束时间。

扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章