英语复习:The earned value technique is a commonly used method of performance measurement.
来源:信管网 2013年10月17日 【所有评论 分享到微信
The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, it means that   ).
 A、the project is ahead of its planned schedule
 B、less work was completed than was planned
 C、the cost overrun for work completed
 D、the cost under-run of performance to date
挣值技术是一种通用的绩效测量方法。它将项目范围、成本、进度整合在一起,帮助项目管理团队评估项目绩效。SPI值若小于1则表示实际进度落后于计划进度。
earned value technique:挣值技术
performance measurement:绩效测量
integrates:整合
scope:范围
cost:成本
schedule:进度
project management team:项目团队
assess:评估
project performance:项目绩效
Schedule Performance Index(SPI=EV/PV):进度执行(绩效)指标
less than:小于
ahead:超前
overrun:超支
扫码关注公众号

温馨提示:因考试政策、内容不断变化与调整,信管网网站提供的以上信息仅供参考,如有异议,请以权威部门公布的内容为准!

信管网致力于为广大信管从业人员、爱好者、大学生提供专业、高质量的课程和服务,解决其考试证书、技能提升和就业的需求。

信管网软考课程由信管网依托10年专业软考教研倾力打造,官方教材参编作者和资深讲师坐镇,通过深研历年考试出题规律与考试大纲,深挖核心知识与高频考点,为学员考试保驾护航。面授、直播&录播,多种班型灵活学习,满足不同学员考证需求,降低课程学习难度,使学习效果事半功倍。

相关内容

发表评论  查看完整评论  

推荐文章