To ensure the project team provide the functionlity the customer expects in a new prece of software, the project manager ask the customer for sing-off on the design crieria.There documents are(   ).
A.technical speifications
B.performance specifications
C.product descriptions
D.quality assurance


相关试题

72题:

Information is no good to you if you can't (    ) it.The location dimension of information means having access to access to information no where you are.
A. access
B. make
C. learn
D. bring

答案解析与讨论:www.cnitpm.com/st/942325.html

73题:

Project manager believes that modifying the project scop may provide added value for the customer.The project manager should(    ).
A.change the scope baseline
B.contact the customer to determine if the change adds value
C.call a meeting of the change control board
D.change the project's objectives

答案解析与讨论:www.cnitpm.com/st/943325.html

74题:

(    ) describees,indetail,the project's deliverables and the work required to create those deliverables.
A.Product scope description
B.Project objectives
C.Produce specification
D.The project scope statement