Serialization delay and  (1)  delay are the two components of network delay that are improved by increasing bandwidth. Serialization delay, i.e. the amount of time it takes to put the  (2)  on the wire, and queuing delay (depth of the queue) are improved by increasing the  (3)  from a 128kbps circuit to a T1. However, three other components of delay, routing/switching delay, distance delay, and protocol delay are components that can not be positively affected by an  (4)  in bandwidth. If the circuits are not over-utilized, then increasing the bandwidth to improve the  (5)  of the application will only result in an increased bandwidth with no positive effects on performance.
(1)A、buffering
B、queuing
C、receiving
D、timing
(2)A、electricity
B、digital
C、data
D、variable
(3)A、memory
B、cache
C、bandwidth
D、delay
(4)A、increase
B、decrease
C、maintenance
D、extension
(5)A、capability
B、cost
C、amount
D、performance

查看答案

相关试题

67题:

计算机系统中广泛采用了RAID技术,在各种RAID技术中,磁盘容量利用率最低的是 ( ) 。
A、RAID0
B、RAID1
C、RAID3
D、RAID5

答案解析与讨论:www.cnitpm.com/st/87193002.html

68题:

以下协议中属于传输层的是 ( ) 。
A、UCP
B、UDP
C、TDP
D、TDC

答案解析与讨论:www.cnitpm.com/st/87203002.html

69题:

下图为某系统集成项目的网络工程计划图,从图可知项目最短工期为 (1) 天,至少需要投入 (2) 人才能完成该项目(假设每个技术人员均能胜任每项工作)。

(1)A、5
B、7
C、8
D、10
(2)A、2
B、4
C、6
D、8

答案解析与讨论:www.cnitpm.com/st/87213003.html