试卷年份2011年下半年
试题题型【单选题】
试题内容

In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has (  ) potential communication channels.
A、10
B、45
C、50
D、100