软题库 学习课程
当前位置:信管网 >> 在线考试中心 >> 信息系统监理师题库 >> 试题查看
试卷年份2020年下半年
试题题型【单选题】
试题内容

()is the Budgeted amount for the work actually completed on the schedule activity or WBS component during a given period.In project time management processes,()involves identifying and documenting the relationships between project activities.()in not inc1uded in Control Quality input documents.Both TCP and UDP belong to()layer of the OSI mode.Cloud computing provides on-demand service to users by using distributed computing and()resource management.
A.activity defifinition
B.activity sequencing
C.schedule control
D.schedule development

查看答案

相关试题

76题: ()is the Budgeted amount for the work actually completed on the schedule activity or WBS component during a given period.In project time management processes,()involves identifying and documenting the relationships between project activities.()in not inc1uded in Control Quality input documents.Both TCP and UDP belong to()layer of the OSI mode.Cloud computing provides on-demand service to users by using distributed computing and()resource management.
A.network
B.virtual
C.centralized
D.specialized
答案解析与讨论:www.cnitpm.com/st/6803918071.html

77题: ()is the Budgeted amount for the work actually completed on the schedule activity or WBS component during a given period.In project time management processes,()involves identifying and documenting the relationships between project activities.()in not inc1uded in Control Quality input documents.Both TCP and UDP belong to()layer of the OSI mode.Cloud computing provides on-demand service to users by using distributed computing and()resource management.
A.session
B.transport
C.network
D.data link
答案解析与讨论:www.cnitpm.com/st/68040435.html

78题: ()is the Budgeted amount for the work actually completed on the schedule activity or WBS component during a given period.In project time management processes,()involves identifying and documenting the relationships between project activities.()in not inc1uded in Control Quality input documents.Both TCP and UDP belong to()layer of the OSI mode.Cloud computing provides on-demand service to users by using distributed computing and()resource management.
A.Project management plan
B.Project documents
C.Quality problems report
D.Work performance data
答案解析与讨论:www.cnitpm.com/st/680414557.html

80题: ()is the Budgeted amount for the work actually completed on the schedule activity or WBS component during a given period.In project time management processes,()involves identifying and documenting the relationships between project activities.()in not inc1uded in Control Quality input documents.Both TCP and UDP belong to()layer of the OSI mode.Cloud computing provides on-demand service to users by using distributed computing and()resource management.
A.Planned value
B.Actual cost
C.Earned value
D.Cost variance
答案解析与讨论:www.cnitpm.com/st/680438764.html