70题: 某项目有4个硬件的生产任务需要完成,有4个硬件厂商可选择,每个厂商只能分配一个任务。下表是各厂商完成各硬件生产所需的时间:

则4个硬件生产完成的总时间最短为( )
A.25
B.26
C.27
D.28
答案解析与讨论:
www.cnitpm.com/st/6330625892.html第
71题: ( )uses the data and results from the( )process to reflect the overall quality status of the project to the stakeholders.
A.Control Quality plan, Quality Management
B.Plan Quality Management, ManageQuality
C.Manage Quality,Control Quality
D.Control Quality, Manage Quality
答案解析与讨论:
www.cnitpm.com/st/6330724148.html第
72题: How frequently the risks are being reviewed ,this should recorded in( ).
A.Risk Management Plan
B.Issue Log
C.Risk Register
D.Risk Report
答案解析与讨论:
www.cnitpm.com/st/6330825426.html第
74题: ( )is the process of specifying the approach and identifying potential sellers.
A. Plan Procurement Management
B. Close Procurement Management
C. Control Procurement
D. Conduct Procurement
答案解析与讨论:
www.cnitpm.com/st/6331026083.html第
75题: The project manager should use( )tool for the purpose toreporton the work remaining for projects.
A.cumulative flow diagram
B.burndown chart
C.forecast estimation
D.earned value
答案解析与讨论: