软题库 学习课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷年份2024年上半年
试题题型【单选题】
试题内容

Project Communications Management consists of two parts. The first part is developing a strategy to ensure communication is effective for stakeholders. The second part is carrying out the activities necessary to implement the( ).
A.  communication tools
B.  communication technology
C.  communication cost
D.  communication strategy

查看答案

相关试题

70题: 某项目有4个硬件的生产任务需要完成,有4个硬件厂商可选择,每个厂商只能分配一个任务。下表是各厂商完成各硬件生产所需的时间:

则4个硬件生产完成的总时间最短为( )
A.25
B.26
C.27
D.28
答案解析与讨论:www.cnitpm.com/st/6330625892.html

71题: ( )uses the data and results from the( )process to reflect the overall quality status of the project to the  stakeholders.
A.Control Quality plan, Quality Management
B.Plan Quality Management, ManageQuality
C.Manage Quality,Control Quality
D.Control Quality, Manage Quality
答案解析与讨论:www.cnitpm.com/st/6330724148.html

72题: How frequently the risks are being reviewed ,this should recorded in(   ).
A.Risk Management Plan
B.Issue Log
C.Risk Register
D.Risk Report
答案解析与讨论:www.cnitpm.com/st/6330825426.html

74题: ( )is the process of specifying the approach and identifying potential sellers.
A.  Plan Procurement Management
B.  Close Procurement Management
C.  Control Procurement
D.  Conduct Procurement
答案解析与讨论:www.cnitpm.com/st/6331026083.html

75题: The project manager should use( )tool for the purpose toreporton the work remaining for projects.
A.cumulative flow diagram
B.burndown chart
C.forecast estimation
D.earned value
答案解析与讨论:www.cnitpm.com/st/6331126131.html