Project manager realizes that the development cost is Already over budget, The project manager should() A.stop the development B.tailor the scope of the Project C.accept the budget And continue the development D.submitA change request
第28题: The Purpose of ()is to ensure that the organization undertakes the right projects And Allocates critical resources Appropriately. A.OPM B.SPM C.VPM D.TPM 答案解析与讨论:www.cnitpm.com/st/5786920591.html