71题: ( )is/are not the outputs of the process Develop Team.
A.Team performance assessment
B.Chance Requests
C.Organizatiomal Process Assets
D.Project Management Plan Updates
答案解析与讨论:
www.cnitpm.com/st/576399062.html第
72题: ( )is not the way to strengthen data security in the era of big data.
A.Build up network security information sharing platform
B.Use trusted products and services
C.Set up a big data security evaluation system
D.Improve the big data industrial chain
答案解析与讨论:
www.cnitpm.com/st/57640237.html第
73题: ( )is/are not the output of plan quality management.
A.Enterprise Environment Factors
B.Project Document Updates
C.Quality Matrix
D.Project Management Plan Updates
答案解析与讨论:
www.cnitpm.com/st/576416831.html第
75题: ( )is the process of identifying and documenting the specific actions to beperformed toproduce the project deliverable.
A.Plan schedule management
B.Develop Schedule
C.Sequence Activities
D.Define Activities