第
69题: 国家标准的制定有一套正常程序,分为预阶段、立项阶段、()阶段、征求意见阶段、审查阶段、批准阶段、()阶段、复审阶段及废止阶段。
A.起草 执行
B.调研 执行
C.调研 出版
D.起草 出版
答案解析与讨论:
www.cnitpm.com/st/5700115436.html第
70题: ()是在工业和信息化部、国家标准化管理委负会的联合指导下研制的,是我国IT服务行业最佳实践的总结和提升。
A.COBIT
B.ITIL
C.ITSS
D.PMBOK
答案解析与讨论:
www.cnitpm.com/st/570024335.html第
71题: Any one or any group of activities utilizing resources totransfer input into output can be viewed as a ()。
A.system
B.structure
C.procedure
D.process
答案解析与讨论:
www.cnitpm.com/st/570032071.html第
73题: The IT service manager has learned that a software canimprove the efficiency of current and future project tasks. Because the software is fresh to the Company. Theengineer is not familiar with the software. The lT service manager decides to send the highest level engineero attend the external training course. The proiect manager uses () risk strategies。
A.mitigation
B.enhancement
C.development
D.sharing
答案解析与讨论:
www.cnitpm.com/st/5700520940.html第
74题: ()is closet to Deming's definition of Quality。
A.Conformance to requirements
B.Fitness for use
C.Continuousimprovement of products and services
D.Customer focus
答案解析与讨论:
www.cnitpm.com/st/5700623678.html第
75题: The IT service manager resigns from a project that meets the scheduleand budget. After hiring an alternativenew manager, the team is opposed to the comments from the new manager. The team is at () developmentstages。
A.Forming
B.Storming
C.Norming
D.Performing
答案解析与讨论:
www.cnitpm.com/st/5700714462.html