The creation of a work breakdown structure(WBS)is the process of(  )the major project deliverables.
A.subdividing
B.assessing
C.planning
D.integrating


相关试题

69题:

The strategies for handling risk comprise of two main types:negative risks, and positive risks.The goal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies(  ),Transfer ,Mitigate .
A.Challenge
B.Exploit
C.Avoid
D.Enhance

答案解析与讨论:www.cnitpm.com/st/545188.html

70题:

(  )is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.
A.Method
B.Polymorphism
C.Inheritance
D.Encapsulation

答案解析与讨论:www.cnitpm.com/st/546188.html

71题:

The Unified Modeling Language is a standard graphical language for modeling object-oriented software.(  )can show the behavior of systems in terms of how objects interact with each other.
A.Class diagram
B.Component diagram
C.Sequence diagram
D.Use case diagram