72题: In (),the project scope,time,and cost are determined in the early phases of the life cycle.Any changes to the scope are carefully managed.
A.predictive life cycle
B.iterative life cycle
C.incremental life cycle
D.adaptive life cycle
答案解析与讨论:
www.cnitpm.com/st/5368223886.html第
73题: Project () includes making choices about resource allocation balancing competing demands examining any alternative approaches tailoring the processes to meet the project objectives and managing the inter dependencies among the Project Management
Knowledge Areas.
A.schedule management
B.scope management
C.integration management
D.resource management
答案解析与讨论:
www.cnitpm.com/st/5368311042.html第
74题: ()refers to the management of the overall and long-term development direction objectives tasks and policies of an organization in a certain period,as well as the corresponding decisions on the organization's resource allocation,and the tracking, supervision and change of these decisions.
A.Quality management
B.Communication management
C.Risk management
D.Strategy management
答案解析与讨论: