软题库 培训课程
试卷年份2022年下半年
试题题型【单选题】
试题内容

In (),the project scope,time,and cost are determined in the early phases of the life cycle.Any changes to the scope are carefully managed.
A.predictive life cycle
B.iterative life cycle
C.incremental life cycle
D.adaptive life cycle

查看答案

相关试题

69题: ()不属于物理安全管理。
A.机房安装监控系统
B.严格控制对应用系统的访问
C.机房安装UPS备用电源。
D.采取必要措施,发现线路截获事件井报警

答案解析与讨论:www.cnitpm.com/st/5367928072.html

70题: 我国国家标准由()进行管理。
A.IEC
B.IEEE
C.SAC
D.W3C
答案解析与讨论:www.cnitpm.com/st/5368012611.html

71题: can be described by the following characteristics:volume,variety,velocity,veracity and value.
A.Artificial intelligence
B.Integrated circuit
C.Parallel computing
D.Big data

答案解析与讨论:www.cnitpm.com/st/5368125490.html

73题: Project () includes making choices about resource allocation balancing competing demands examining any alternative approaches tailoring the processes to meet the project objectives and managing the inter dependencies among the Project Management
Knowledge Areas.
A.schedule management
B.scope management
C.integration management
D.resource management
答案解析与讨论:www.cnitpm.com/st/5368311042.html

74题: ()refers to the management of the overall and long-term development direction objectives tasks and policies of an organization in a certain period,as well as the corresponding decisions on the organization's resource allocation,and the tracking, supervision and change of these decisions.
A.Quality management
B.Communication management
C.Risk management
D.Strategy management
答案解析与讨论:www.cnitpm.com/st/536849195.html

75题: ()is not the communication technical that may be used for the virtual team.
A.Shared portals
B.Face to face talk
C.Video conference
D.E-mail/chat