A Project has been temporarily stopped due to unforeseen community disagreements. Since this was not identified as a risk during the project planning phase. It was not included in the risk register.What should the project manager do?
由于不可预见的社区反对意见,一个项目暂时停止,由于在项目规划阶段没有将其识别为一项风险,因此未将其纳入风险登记册。项目经理应该怎么做?
◑A.Recommend mitigation options to the stakeholders obtained via meetings and brainstorming通过会议和头脑风暴向相关方推荐减轻措施
◑B.Replan the remaining work, and reschedule the outstanding tasks and completion date.重新计划剩余工作,并为未完成的任务和完成日期重新制定进度计划
◑C.Escalate the matter to the project sponsor and functional manager将该事项升级上报给项目发起人和职能经理
◑D.Meet with stakeholders to review various contingency options, and then recommend the appropriate actions与相关方开会以审查各种应急方案,然后推荐适当的措施