试卷年份2020年下半年
试题题型【单选题】
试题内容

()is the process of formalizing acceptance of the completed project deliverables. The key benefit of this process is that it brings objectivity to the acceptance process and increases the probability of final product, service, or result acceptance by validating each deliverable。
A、 Validate scope
B、Define scope
C、Control scope
D、Collect requirement

查看答案

相关试题

70题: ()can be scripted as a new science and technology,which is used to simulate human intelligence namely, computers simulate the way of human’s thinking and intelligent behavior, such as learning, reasoning thinking, planning,and so on 。
A.internet of things
B.cloud computing
C.artificial intelligence
D.big data
答案解析与讨论:www.cnitpm.com/st/432248048.html

71题: ()is preservation of confidentiality, integrity and availability of
information,in addition, other properties such as authenticity, accountability, non-repudiation and reliability can also be involved。
A、 Equipment security
B、Network security
C、Information security
D、Content security
答案解析与讨论:www.cnitpm.com/st/4322516727.html

72题: () involves  choosing part of a population of interest for inspection
A、 Check list
B、 Check sheet
C、Statistical sampling
D、Questionnaire
答案解析与讨论:www.cnitpm.com/st/4322625747.html