试卷年份2008年下半年
试题题型【单选题】
试题内容

Project work packages are typically decomposed into smaller componentscalled activities to provide a basis for (  ), scheduling, executing, and monitoring and controlling the project work.
A. reviewing
B. estimating
C. auditing
D. expecting