70题: 某系统集成企业在项目实施阶段出现突发情况,引起进度问题。此时监理单位应通过( ),督促各方采取应急措施赶上进度要求,以便项目的开发能以预期进度完成。
A.监理日报
B.监理周报
C.监理月报
D.监理专题会议
答案解析与讨论:
www.cnitpm.com/st/405657128.html第
71题: ( )techniques are used to find ways to bring project activities that are behind into alignment with the plan by fast tracking or crashing the schedule for the remaining work .
A. Schedule forecasts
B. Schedule compression
C. Change requests
D. Data analysis
答案解析与讨论:
www.cnitpm.com/st/4056616420.html第
72题: Generally, the contract claim can be settled amicably through negotiation. If no compromise can be reached, the dispute can be settled by ( ).
A. negotiation
B. the court
C. lawyer
D. arbitration
答案解析与讨论:
www.cnitpm.com/st/4056723685.html第
74题: Much of the effort of cost control involves analyzing the relationship between the consumption of project funds and the work being accomplished for such expenditures. The key to effective cost control is the management of the approved ( ).
A. schedule baseline
B. cost baseline
C. cost output
D. cost input
答案解析与讨论:
www.cnitpm.com/st/4056914819.html第
75题: The top management of a company will review the organization’s management system, the management review will include consideration of :
( a ) customer feedback on quality
( b ) processes performance and product conformity
The purpose of management review is ( ).
A
. control of customers
B. control of measurements
C. control of qualities
D. control of opportunities
答案解析与讨论: