( ) is a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. A. Analogous estimatingB. Parametric estimatingC. Three-Point estimatingD. Bottom-Up estimating
信管网参考答案:A(仅供参考,欢迎评论交流) 收藏