试卷年份2018年上半年
试题题型【单选题】
试题内容

Estimate Activity Durations is the process of estimating the number of work periods to complete indivities with estimated resources . The tools and technques is not including().
A、expert judgment
B、analogous estimating
C、requirements traceability matrix
D、three-point estimating

查看答案

相关试题

68题: ()is the technology that appears to emulate human performance typicaliy by learning,coming to its own conclusions, appearing to understand complex content, engaging in natural dialogs with people, enhancing human cognittive performance (also known as cognittive computing) or replacing people on execution ofnonroutine tasks.
A、Cloud service
B、Blockchain
C、Internet of things
D、Artificial intellingence
答案解析与讨论:www.cnitpm.com/st/3875928655.html

69题: ()is a decentralized, distributed and public digital ledger that is used to record transactions across many computers so that the record cannot be alterred retroactively without the alteration of all subsequent blocks and the collusion  of the network.
A、Cloud service
B、Blockchain
C、Internet of things
D、Artificial intellingence
答案解析与讨论:www.cnitpm.com/st/387603471.html

70题: () includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . Managing the project scope is primarily concerned with defining and controlling what is not included in the project.
A、Create scope
B、Project stakeholder management
C、Preject scope management
D、Project cost management
答案解析与讨论:www.cnitpm.com/st/387618338.html

72题: () The process of translating the quality mangement plan into executable quality activities that incorporate the organization's quality policies into the project.
A、Manage quality
B、Quality audit
C、Quality metrics
D、Quality improvement
答案解析与讨论:www.cnitpm.com/st/3876324170.html