A project manager is quantifying risk for her project. Several of her experts are offsite, but wish to be included. How can this be done?
A、Use Monte Carlo analysis using the Internet as a tool.
B、Apply the critical path method.
C、Determine options for recommended corrective action.
D、Apply the Delphi Technique