软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 2017年信息系统项目管理师最新英语模拟题(7)
考试中心《2017年信息系统项目管理师最新英语模拟题(7)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A project health check identified a risk that your project would not be completed on time. Several projects are competing for the same resources, and a serious resource conflict is emerging. As a result, you are quantifying the project’s risk exposure and determining what cost and schedule contingency reserves might be needed. You performed a schedule risk analysis using Monte Carlo analysis. The basis for your schedule risk analysis is the:
A、WBS
B、Gantt chart
C、Schedule network diagram and duration estimates
D、Probability/impact risk rating matrix


相关试题

推荐文章
合作网站内容