During project execution, the project manager observes that a particular resource is underutilized. Resource leveling aims to do which of the following?
A、Minimizes the variations in resource loading
B、Maximizes the variations in resource loading
C、Minimizes the loading of resources
D、Maximizes the motivation of resources