On larger projects, a Responsibility Assignment Matrix(RAM)can be developed at various levels. Which option exemplifies the RAM’s levels?
A、High-level can define a project team group or unit is responsible for within each component of the WBS, while lower-level are used within the group to designate roles, responsibilities, and levels of authority for specific activities.
B、Lower level is used only to designate levels of authority for specific activities.
C、All levels are used to designate roles, responsibilities, and levels of authority for specific activities.
D、High level allows a person to see all activities associated with one person.