A customer asks the project manager add three small requirements to the project. The project manager believes these small requirements could be done as part of the current baseline plan and would not impact project resources, cost and time lines. The project manager should do which of the following?
A、Include these new requirement and continue to deliver them.
B、Document the request and have the project team analyze it.
C、Ask for more time or money from the customer just in case.
D、Accept the new requirements and inform all stakeholders of the change