软题库 移动APP 扫码下载APP 随时随地移动学习 培训课程
当前位置:信管网 >> 在线考试中心 >> 信息系统项目管理师题库 >> 试题查看
试卷名称 2017年信息系统项目管理师最新英语模拟题(6)
考试中心《2017年信息系统项目管理师最新英语模拟题(6)》在线考试
试卷年份2017年下半年
试题题型【单选题】
试题内容

A customer asks the project manager add three small requirements to the project. The project manager believes these small requirements could be done as part of the current baseline plan and would not impact project resources, cost and time lines. The project manager should do which of the following?
A、Include these new requirement and continue to deliver them.
B、Document the request and have the project team analyze it.
C、Ask for more time or money from the customer just in case.
D、Accept the new requirements and inform all stakeholders of the change


相关试题

推荐文章
合作网站内容