Your employee is three days late with a report. Five minutes before the meeting where the topic of the report is to be discussed, she hands you the report. You notice some serious errors in it. What should you do?
A、Cancel the meeting and reschedule when the report is fixed.
B、Go to the meeting and tell the other attendees there are errors in the report
C、Force the employee to do the presentation and remain silent as the other attendees find the errors.
D、Cancel the meeting and rewrite the report yourself.