A project is a week behind schedule because an engineer is not familiar with some of the technology. The project manager assigns a senior resource to mentor the engineer and documents it in the project management plan. This is an example of which of the following?
A、Work performance information
B、Expert judgment
C、Corrective action
D、Preventive action