Which of the following options describes contingency reserve?
A、Budget reserved for unplanned changes to project scope and cost.
B、Budget reserved for covering poor performance.
C、Budget reserved for unplanned but potential required changes that can result from realized risks identified in the risk register.
D、Budget reserved for covering cost overrun due to approved changes.